Our Pool Renovation Album / Dec 2022-Mar 2023

 Check back regularly for updates!

Week 1 Dec 5th to Dec 9th 2022

(Click on photos for a slideshow.)

  • Pool Draining
  • Ginger Ln Closure - Rainbow
  • Took almost 24 hours to drain this far.
  • 12/6/2022
  • 12/6/2022
  • 12/6/2022
  • 12/6/2022
  • 12/6/2022
  • 12/6/2022
  • 12/7/2022
  • 12/7/2022
  • 12/7/2022
  • 12/7/2022
  • 12/7/2022
  • 12/7/2022
  • 12/7/2022
  • Protecting the floors
  • More floor protection.
  • Putting EVERYTHING under wraps

Week 2 Dec 12th to Dec 16th 2022

(Click on photos for a slideshow.) 


Week 3 Dec 19th to Dec 23rd 2022

(Click on photos for a slideshow.) 

Week 4 skipped due to our Christmas/New Year Shutdown

Week 5 Jan 3rd to Jan 6th 2023

(Click on photos for a slideshow.) 


Week 6 Jan 9th to Jan 13th 2023

(Click on photos for a slideshow.)

  • Tile samples and their purpose.
  • New LED underwater light
  • 20230113_161942_445

Week 7 Jan 17th to Jan 20th
(Mon. Jan 16th was MLK Day)

(Click on photos for a slideshow.)  

Week 8 Jan 23th to Jan 27th
(Tiling in the last few days is a slow and tedious job!)

(click on photos for a slideshow)

Week 9 Jan 30th to Feb 3rd
(More tiling....further progress....)

(click on photos for a slideshow)

Week 10 Feb 6th to Feb 10th
(Tiling of gutters and coping almost done!)

Week 11 Feb 13th to Feb 20th
(Tiling continues....)


More historical pictures and an article about TC's past:
Excerpts From California Architecture Jan/Feb 1982 [pdf]

Week 12 Feb 20th to Feb 24th
(Working on the ladders and steps...)


Week 13 Feb 27th to Mar 3rd
(Plastering finished over the weekend ....)

BTW - Water is still being conditioned and is cold so you can't jump in for a couple of weeks...